    Hi,

    I am planning on doing a VSM at our printing company for a specific customer ( we have loads) and am looking at ideas /thoughts on how to go about it.

    1) The customer has hundreds of SKU's, is there a better approach to focus on 2 - 3 SKU's ( I used the judgement of most commonly used ( volume) & repeatability & those which use most of the machines ).
    2) What is the Unit to consider, should it be each label / each order( could have hundreds of labels) / any other way - I am looking at the process right from inventory coming in ( Paper boards) to the cartons / leaflets leaving the factory.
    3) What is the typical OEE of machines at each of the different kinds of machines used in the printing world ( we make cartons and leaflets).
    4) What would be key things for me to look out for since this is out first VSM in 4 years ( no clue what VSM was done earlier but am told it was done )

    Any thoughts would be greatly appreciated.

    Rgds,
    Tom

  2. #2
    amgd1972's Avatar
    amgd1972 is offline Junior Member
    Join Date
    Aug 2009
    Location
    Ireland
    Posts
    26

    Default

    Hi Tom,


    1. I would break the SKU's down into product type and pick the big / high value runners.

    2. ?? - would need to know more about your situation

    3. target OEE for equipment is 65%, WCM 85% - however you will struggle to hit those target is you have multiple set ups per shift. I use OEE to flag areas of concern, don't use it as a goal line, much the the annoyance of the department heads, they all want 100%.

    4. ?? - would need to know more about your situation

    A.

  3. #3
    thmurphy is offline Junior Member
    Join Date
    Jun 2011
    Posts
    5

    Default LEAN @ Printing Company

    1) Thats perfect .. works inline with what i was thinking. I have selected the product with the max volume for the customer in question.
    2) When we do a VSM, i was told that the unit being considered should be the same across the stream ..is this true ? Eg, in this case the board received is the unit flowing through which changes form at various stages ...ultimately ending up as x number of cartons.
    3) When i calculate OEE should it be for each machine .. printer, cutter , Folding & Packing ? .. How do i / Can I roll all these into one single score to reflect the process OEE.?
    4) Not sure if you have done a VSM earlier in the printing cartons and labels field .. if so, any insights would be great .. what are typical opportunites etc ?

    Rgds,
    Tom

  4. #4
    daveholmes is offline Junior Member
    Join Date
    Sep 2011
    Posts
    15

    Default

    Hi

    I utilise the most current lean manufacturing methods if your based in the UK feel free to visit my factory for more info

    Label Printing and Bespoke Printed Labels


Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  

Sponsors

Esko Sponsored Content