OK, it's been a very, very long time since I've posted. Or it seems like a long time. We're purchasing a new guilotine and it should be arriving around Christmas day or a little after. It won't fit where our current guilotine is, and I have always said that the guilotine needed to be placed in a different place anyway, since we walk twice the length of factory for every job in some cases.
So I'm taking advantage and have really pushed for a factory re-arrange. Im madly trying to place everything correctly and have actually built a 3D model of the front factory and all of our equipment. Some benches have been ommitted since I believe they are just 'junk magnets'. "Where am I going to put this junk? Oh, here's a place"
Here are some photo's of the overall factory. (the main 4 colour press is not moving, neither is the console). Just about everything else can move. This is my current progress.
This first image is of the overall factory at my current re-arrange progress
This is a close of up of the GTO/NCR cell. The Stapler is currently 'inside' the bench as I'm considering cutting the bench to fit it in that position.
This is a close up of the Sakurai, Guilotine, folder and Collator.
This was all created in the FREE 3D application by Google called Google sketchup. I just dug in and learnt it as fast as I could and its seriously the easiest 3D I've ever used. I created all this in just over 2 solid weeks.
If you'd like to move around in a 3D model of our factory you can download my SKP file:
http://www.hollands.com.au/GoogleSketchup/FactoryIn3D.skp
And download either,
The FREE Viewer Application:
Google SketchUp Viewer
Or Actually Google Sketchup (FREE) which should allow you to edit aswell:
Google SketchUp Website
At this stage I'm putting it out there to see if there are any comments. Kinda looking for some inspiration aswell!
OK, it's been a very, very long time since I've posted. Or it seems like a long time. We're purchasing a new guilotine and it should be arriving around Christmas day or a little after. It won't fit where our current guilotine is, and I have always said that the guilotine needed to be placed in a different place anyway, since we walk twice the length of factory for every job in some cases.
So I'm taking advantage and have really pushed for a factory re-arrange. Im madly trying to place everything correctly and have actually built a 3D model of the front factory and all of our equipment. Some benches have been ommitted since I believe they are just 'junk magnets'. "Where am I going to put this junk? Oh, here's a place"
Here are some photo's of the overall factory. (the main 4 colour press is not moving, neither is the console). Just about everything else can move. This is my current progress.
This first image is of the overall factory at my current re-arrange progress
This is a close of up of the GTO/NCR cell. The Stapler is currently 'inside' the bench as I'm considering cutting the bench to fit it in that position.
This is a close up of the Sakurai, Guilotine, folder and Collator.
This was all created in the FREE 3D application by Google called Google sketchup. I just dug in and learnt it as fast as I could and its seriously the easiest 3D I've ever used. I created all this in just over 2 solid weeks.
If you'd like to move around in a 3D model of our factory you can download my SKP file:
http://www.hollands.com.au/GoogleSketchup/FactoryIn3D.skp
And download either,
The FREE Viewer Application:
Google SketchUp Viewer
Or Actually Google Sketchup (FREE) which should allow you to edit aswell:
Google SketchUp Website
At this stage I'm putting it out there to see if there are any comments. Kinda looking for some inspiration aswell!